Give the pump allowance a deadline
On a fiberglass pool contract covered by Massachusetts Chapter 142A, give the pump allowance and the advance cover order separate lines. In a $36,000 contract, for example, include a $2,000 pump allowance for a model the homeowner will choose by July 10. State whether freight and installation are included. List the custom cover separately, with its price and the date the supplier needs the order.
Document the cover cost and lead time
Keep the supplier’s $15,000 quote and written lead time with the contract. In this example, the cover must be ordered before work begins to meet the scheduled completion date. The state’s sample contract calls for the description and dollar amount of items that must be special-ordered in advance.
Chapter 142A, Section 2 caps the entire required pre-work deposit at the greater of one-third of the contract price or the actual cost of qualifying items. Here, the cap is $15,000 because the documented qualifying cost exceeds $12,000. Ask the Massachusetts Home Improvement Contractor Program about uncertain coverage or deposit treatment before collecting payment.
Show the deposit credit and pump adjustment
If the homeowner approves a $2,300 pump, record the $300 increase before ordering. On the July 15 invoice, show the revised contract total of $36,300, the $15,000 deposit already paid for the cover order, and the $21,300 remaining balance. Carry the approved adjustment into the dated payment schedule so the owner can see what is due at each installment.