Name the drawing and scope line being revised
Suppose a Needham homeowner wants to move the patio edge and shift the pool barrier before work starts. Needham’s permit checklist calls for the pool and barrier to appear on the surveyor-certified plot plan. Ask the building office whether it needs revised documents, and identify who will coordinate them. In the change order, reference the signed contract, the original drawing, and the proposed revision. Spell out which work is added or removed and whether document revisions are included. Swimming Pools | Needham, MA Home Improvement Contract Sample Language | Mass.gov
Carry the revision through to the balance
Show the credit for omitted work and the charge for added work, then give the net change and the revised contract total. Massachusetts sample language for registered home improvement contracts calls for start and completion dates and payment dates and amounts. Use those same fields to show where the change lands. If the revision moves the completion date or changes the next installment, record the revised date and dollar amount on the change order.
Send one approved version to the crew and office
Get both parties’ signatures on the change and give the homeowner a copy before releasing the revised work. Send the signed revision and its drawing together to the crew, scheduler, and billing contact. If the homeowner declines the change, mark the request as declined in the job file and confirm which drawing the crew should use.